Offtaker of Electricity
Chugoku Electric Power Company
Scale of Power Generation
257.7 MWdc
Location
Mimasaka-shi, Okayama-ken
Project Finance
Sumitomo Mitsui Trust Bank, Ltd.
Date of Facility Certification
March 16, 2015
Commencement of Construction
April 2017
Date of Commercial Operation
December 27, 2019