Offtaker of Electricity
TEPCO Energy Partner, Inc.
Scale of Power Generation
53.9 MWdc
Location
Sano-shi, Tochigi-ken
EPC Contractor
Juwi Shizen Energy Inc.
Project Finance
Sumitomo Mitsui Trust Bank
Date of Facility Certification
March 30, 2015
Commencement of Construction
October 2020
Date of Commercial Operation
May 9, 2022